WASTEWATER TREATMENT PLANT (WWTP) PROJECT

WASTEWATER TREATMENT PLANT COST ESTIMATE

The wastewater treatment plant cost estimate is still rough, but is in the range of $5.25 to $6.0 million.  It is composed of three main cost components: (1) Flume Improvements – $300,000 to $350,000, (2) Biosolids Removal, $600,000 to $800,000, and (3) WWTP Construction and overall Project/Construction Management, $4,500,000.  Only element #1 is a reasonably firm estimate at this time.  DEQ needs to accept our plans for elements #2 & #3 before the estimates for these aspects of the project can firm up.   In addition, there are construction management costs, testing, reporting etc. that will add $300,000 to these costs for a two year  project. Read More